Week 42, Day 4

Week 42, Day 4:

  • More progress on the zinc roofing though again restricted by the weather and slowed up by the fiddly detailing around the roof windows
    • The photo shows the contrast between the fresh-from-the-mill zinc and the material that has been in the weather for just a week
  • More plastering – now just one room left to finish (the ground floor shower room)
  • Extending the oak flooring in the office on to the landing
  • More wall tiling in the first-floor bathroom
  • More electrical second-fix in the kitchen, now as complete as it can be pending the installation of the worktops (originally planned for today but now due tomorrow)
Week 42, Day 4

Week 42, Day 4

Zinc roofing is now just past the roof windows

Zinc roofing is now just past the roof windows

Plaster scratch coat in the ground floor shower room, the last one to be plastered

Plaster scratch coat in the ground floor shower room, the last one to be plastered

CC BY-SA 4.0 Week 42, Day 4 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.