Week 44, Day 3

Week 44, Day 3:

  • Completion of the Solar Shading (the round-the-corner section at the far left of the main photo)
  • More electrical second-fix, including connecting the Induction Hob (which had been waiting on the replacement island worktop), lots more sockets and the start of work on the electrical boards on the First Floor
  • More skirtings, architraves and internal window boards
Week 44, Day 3

Week 44, Day 3

Solar shading at the south-west corner

Solar shading at the south-west corner

Day 1 of installing the electrical boards on the First Floor

Day 1 of installing the electrical boards on the First Floor

CC BY-SA 4.0 Week 44, Day 3 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.