Week 48, Day 3

Week 48, Day 3:

  • Good progress on the balustrade for the balcony, installing the brackets for the handrail and the clamps for the glass panel
  • Some initial preparations for finishing off the staircase
  • Nearing completion with the plumbing for the Ground Source Heat Pump
  • More second-fix electrical, mainly working on the 230V DALI dimmers for the mains-voltage lighting circuits
Week 48, Day 3

Week 48, Day 3

Support posts and clips for the glass balustrade on the balcony

Support posts and clips for the glass balustrade on the balcony

230V DALI dimmers for the First Floor

230V DALI dimmers for the First Floor