Week 53, Day 1:
- Temporarily installing the oak boxes on the ground-to-flrst floor stair treads
- A little more progress on the second-fix electrical which is now nearing completion
Week 53, Day 1 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.