Week 28, Day 5

Week 28, Day 5:

  • The first section of cedar cladding installed on the southern end of the east elevation
  • Continuing to prepare the second floor for plasterboard, installing the vapour-tight membrane under the roof and an air-tight membrane on the gable walls, then installing battens to form a service void and to take the plasterboard
  • More first-fix plumbing and electrical