Week 35, Day 1:
- Lots more rain
- The main event for the day was the installation of the “missing” window on the second floor and the replacement of the two windows originally made with the wrong colour frames
- More electrical first-fix
- Installing some of the contoured panels for the LED strip lights recessed into the ceiling

“Fylo” lighting channel installed in the ceiling – needs another layer of plasterboard to bring it flush