Week 41, Day 4:
- More second-fix electrical, including the installation of some of the LED down-lighters
- More work on the kitchen, including installing the fridge, the main sink, sorting out the placement of the taps and the pop-up sockets and having Midland Stone Centre measure up for the worktops which should be ready in a week
- More finishing up on the balcony, cladding the walls in cedar
- Now that I come to check the photo some of the boards have been stored wet, have discoloured and will need to be replaced
- More plastering in the Living Room