Week 41, Day 4

Week 41, Day 4:

  • More second-fix electrical, including the installation of some of the LED down-lighters
  • More work on the kitchen, including installing the fridge, the main sink, sorting out the placement of the taps and the pop-up sockets and having Midland Stone Centre measure up for the worktops which should be ready in a week
  • More finishing up on the balcony, cladding the walls in cedar
    • Now that I come to check the photo some of the boards have been stored wet, have discoloured and will need to be replaced
  • More plastering in the Living Room
Week 41, Day 4

Week 41, Day 4

One of the LED down-lighters

One of the LED down-lighters (SPOT from BPM Lighting)

Main sink in the kitchen

Main sink in the kitchen, made by BLANCO

 

Cedar cladding around the balcony

Cedar cladding around the balcony

CC BY-SA 4.0 Week 41, Day 4 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.