Week 49, Day 3

Week 49, Day 3:

  • Almost completed on the Ground Source Heat Pump commissioning – all powered up and heating water with just a bit more insulation to finish off
  • Installing the hand rail for the balcony, ready for the glass balustrade
  • More second-fix electrical, connecting up the electric windows on the second floor and more of the wall lights
Week 49, Day 3

Week 49, Day 3

Handrail installed for balcony; just the glass to go

Handrail installed for balcony; just the glass to go

Electric clerestory windows on the second floor

Electric clerestory windows on the second floor

Master bedroom wall lights when illuminated

Master bedroom wall lights when illuminated

CC BY-SA 4.0 Week 49, Day 3 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.