Outbuildings: Week 2, Day 5

Outbuildings: Week 2, Day 5

Little change visible in the overview photo since all today’s work was at the North-Western corner of the site, out of shot at the bottom left.

All the foundation trenches have now been excavated to their target depth. There’s just a bit of tidying up left to do before the concrete goes in on Tuesday 25th March.

Southern foundation trench for the Garage block, with the pad foundation for the outside staircase at the bottom