Outbuildings: Week 6, Day 1

Outbuildings: Week 6, Day 1

Another dry day ahead of the rain forecast for the next few days.

The stone inside the buildings was compacted and ‘blinded’ with a layer of sharp sand – also then compacted. Then the team made a start on installing the damp-proof membrane and the under-floor insulation.