Outbuildings: Week 36, Day 6

Outbuildings: Week 36, Day 6

While weekend working isn’t customary, this is the second weekend where noteworthy progress was made – this time on the block paving, where the team had been busy with other work and were struggling to make time. While it was drizzling all morning – which would have been an issue for bedding paving blocks on sand – these permeable blocks get bedded on 6mm stone chips, which can still be levelled when they’re wet.

First day of progress on the block paving for the parking area by the garages