Outbuildings: Week 38, Day 1

Outbuildings: Week 38, Day 1

The main build team were on site all day sorting out a few of the smaller groundworks tasks:

  • Finishing the installation of the last of the Marshalls GrassGuard blocks around the perimeter of the block-paved parking area
    • There’s around 2/3 of a pack left over but those will be saved for future use
  • Filling in the holes excavated to access the water mains and electrical ducts
  • Clearing a trench around the foul drainage pipe that runs under what-will-be the vehicle access to the parking area, so that can be encased in concrete to maintain its level even with traffic passing relatively closely over the top of it
Completed block-paved parking area with its GrassGuard block perimeter / buffer area which then transitions to topsoil that will grow grass

The right-sized replacement concrete headwall was allegedly due for delivery today but is now said to be coming tomorrow.

CC BY-SA 4.0 Outbuildings: Week 38, Day 1 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.