Week 45, Day 3

Week 45, Day 3:

  • Close to completion on the kitchen installation, with the hob now sealed to the Silestone worktop with heat-resistant silicone and the pop-up power sockets installed in the island worktop
  • The first day of second-fix on the security and fire alarm systems, installing some of the movement and shock sensors
  • More second-fix electrical, installing the last of the PIR sensors for the lights in some of the ground floor rooms
  • More work on the internal doors, drilling out for the door handles and latches
Week 45, Day 3

Week 45, Day 3

Second Floor Landing complete apart from paintwork

Second Floor Landing complete apart from paintwork and staircase balustrade

PIR movement sensor and shock sensor on door frame

PIR movement sensor and shock sensor on door frame

CC BY-SA 4.0 Week 45, Day 3 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.