Outbuildings: Week 3, Day 5

Outbuildings: Week 3, Day 5

Further good progress with the below-DPC walling, starting to add engineering bricks to the outer skin and continuing to lay concrete blocks towards the North-East corner.

Another delivery of concrete blocks and some more ready-mixed mortar.