Outbuildings: Week 6, Day 3

Outbuildings: Week 6, Day 3

After some uncertainty about the weather (which was windy but much less wet than had been forecast a few days previously) the installation of the concrete floor slabs went ahead as planned.

The concrete pump was all set-up and ready by 07:00 then four lorry-loads of concrete were delivered and laid between 08:30 and 11:30.

Pumping concrete to the first part of the floor slab

The specification called for a power-floated finish so a team from UK Concrete Flooring Specialists Ltd were kept busy finishing the surface until sunset.

Power-floating the almost-fully-set concrete