Outbuildings: Week 7, Day 4

Outbuildings: Week 7, Day 4

Foul drainage (the Y-shaped pipework) is now connected into one of the existing inspection chambers for the house and bedded on pea shingle, ready for inspection by Building Control.

Then good progress with the stormwater drainage: the 160mm pipes visible along the eastern (far) side of the workshop, before they were installed.