Inspection by Building Control early in the day which confirmed they were happy with the drain layouts so those are now partially back-filled – initially with pea shingle then (in some places) with excavated material.
Further work to prepare the drainage connections for the rainwater downpipe connections.
Outbuildings: Week 8, Day 1 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.