More progress on the inner skin of cavity-wall blockwork. The walls visible in the photo constitute the full extent of the cavity walling, forming an ‘L’ shape. These are being taken a few courses higher, now the mortar in the lower layers has had chance to fully harden.
Delivery of the first lorry-load (5,000) of facing bricks. The cavity wall insulation boards, delivered yesterday, have been moved into the courtyard to make room for other deliveries so are now visible in the overview photo.
Outbuildings: Week 9, Day 3 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.