Outbuildings: Week 26, Day 1

Outbuildings: Week 26, Day 1

Mortaring the last of the roof tile verges, on the West-facing gable of the Garage block – then some progress installing the guttering.

No further work on the mains electrical installation today but the separate team from the intruder and fire alarm contractor started their first-fix.