Outbuildings: Week 35, Day 5

Outbuildings: Week 35, Day 5

Another day of good progress, with two of the garage door roller shutters now fully operational and another one well on the way. That and the last one should be finished on Monday.

The team from Chellaston Renewables were back on site to fit the external heat pump unit on its wall bracket – not a simple task since it weighs over 60kg, and it’s quite a way off the ground.

External unit for Daikin Air-to-Air heat pump installed on East wall of Workshop