Another very hot day, reaching 34 C by the end of the afternoon, so the build team started and finished an hour earlier than normal to give a bit more working time in the (relatively) cool morning.
More work on the roof structure, installing most of the ‘extensions’ to the roof trusses over the Garage Door arches.

Also more work on the gable walls at the north-east and north-west corners.