Another day of good weather so the ridge tile installation has been completed and some more of the guttering installed. With the ridge tiles fitted, all of the scaffolding is now ready for removal – with the priority being the area around the Garage doors.
The scaffolders removed the central section of scaffolding from the Garage block, allowing access to the guttering it had been blocking. It seems they only brought a small lorry so not all of the removed scaffolding was transported off-site.

While the scaffolding to the South of the Workshop was still in-situ, it was a good opportunity to core-drill the high-level 5″ holes for the intake and exhaust vents for the MVHR system.
A couple more lorry-loads of muck-away and the delivery of the “100mm” loft insulation that will be fitted between the ceiling joists over the Workshop and Utility Room, before the MVHR ducting is installed above that (but below the upper layers of insulation).
Outbuildings: Week 28, Day 5 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.