The main progress today was more second-fix of the alarm system, where most of the physical installation was completed – with the exception of the magnetic contact on one of the roller shutters, because the controller isn’t responding and the door is stuck open (that will get attention from the installers tomorrow) and the radio link to the alarm system in the House.
The automatic reader for the various M-Bus meters was also installed, now the data network is operational.