More second-fixing of the alarm system, installing more sensors in the morning then moving on to the main control panel and zone expander units once those had been delivered, early afternoon.
There was wet and windy weather overnight and for the first part of the morning, which held up progress on the ground works – but has mostly filled the rainwater tank. The team are waiting for delivery of some additional components for the inlets and outlets for the rainwater attenuation pond, which had been promised for delivery yesterday or today but are now (allegedly) due next week. Instead of installing those they completed the tidy-up of the ground to the East side of the building.