The garage door installation team were back on site to finish up the last few bits and pieces, which only took a couple of hours. The Hormann RollMatic 2 shutters have quite a sophisticated motor control system, with a ‘soft stop’ at the bottom of their run and they lift faster than they lower (when they need to be checking for an increase in motor load that might indicate an obstruction). The four-button remote controls have been configured to operate all of the doors from each remote control.
The electrical installation team were also back on site, completing all the outdoor lighting, the last of the indoor lighting, the special sockets for the rainwater harvesting system and some of the work on the two myenergi Zappi electric car chargers. A few more hours tomorrow should see the electrical installation completed – apart from the electric shower, which needs to wait until the wall has been tiled (which needs to wait for the floor covering to go down).

One other bit of progress was a trial fitting of the steel handrail for the external staircase, before that gets fully welded and galvanised. It just needs a couple of adjustments to the fixing brackets – and the ‘return’ section of the rail for the landing needs fabricating.

Outbuildings: Week 36, Day 2 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.