Outbuildings: Week 27, Day 4

Outbuildings: Week 27, Day 4

The scaffolders returned this morning to remove the boards and poles dismantled by the builders yesterday, so now the inside of the Courtyard is free of scaffolding, ready for the installation of the windows and doors in the coming days. (The scaffolding is being retained around the ‘outside’ of the building, to preserve access to fit the ridge tiles – for which the dry-fix ridge tile retaining product choice was finally confirmed mid-afternoon).

More of the rainwater downpipes were installed – as well as the blue engineering bricks (below DPC) for the external staircase and buttresses.

The electrical installation team were also back on-site for the first time in a few days, to continue work in the Garages.

CC BY-SA 4.0 Outbuildings: Week 27, Day 4 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.