Week 26, Day 5

Week 26, Day 5:

  • Boarding out the floor of the balcony (west end of the first floor)
  • Building the wooden cavity wall at the north end of the balcony
  • More electrical first-fix, running mains cables on the second floor
Week 26, Day 5

Week 26, Day 5

Gradient to balcony floor formed using wedge-shaped strips under boards

Gradient to balcony floor formed using wedge-shaped strips under boards

(The above photo taken rather later, after some of the cabling was in place, when I spotted that one of the darker-coloured wooden strips clearly showed the wedge profile.)

Wooden wall at end of balcony

Wooden wall at end of balcony

The wall at the north end of the balcony is effectively part of the cavity wall structure but there’s no supporting masonry underneath so it’s framed in timber in order to be lightweight but it will get filled with cavity wall insulation like the rest of the walls.

Mains and data cable ready for electrical first-fix

Mains and data cable ready for electrical first-fix

Week 26, Day 4

Week 26, Day 4:

  • Framing the stud-work partitions for the first-floor bathrooms
  • Starting the electrical first-fix, for the sockets on the second floor
Week 26, Day 4

Week 26, Day 4

En-suite Bathroom for the Guest Suite

En-suite Bathroom for the Guest Suite

Electrical first-fix on the second floor (Bedroom 5)

Electrical first-fix on the second floor (Bedroom 5)

Temporary polythene cover for the office window

Temporary polythene cover for the office window