Week 18, Day 4

Week 18, Day 4:

  • Much better weather today – bright, sunny and almost feeling warm in the sunshine by the afternoon
  • Not much evidence of progress on the south side because most of the SIPS activity was on the north side
  • In addition to the progress with the Structural Insulated Panels, the two 32mm water supply pipes were routed into the utility room
    • Two because there’s one for the regular mains water (blue MDPE) and a separate pipe for harvested rainwater (black MDPE with a green stripe)
    • Initially these will be connected together (i.e. everything fed from the mains supply) but it’s possible a rainwater harvesting system will be installed when the outbuildings are rebuilt later
Week 18, Day 4

Week 18, Day 4

First water pipe installed and preparation for second pipe

First water pipe installed and preparation for second pipe

Both 32mm water pipes coming through the floor

Both 32mm water pipes coming through the floor

Both pipes will have water meters installed a little above the top of the floor slab. The thicker pipes on the right are the “brine” pipes for the Ground Source Heat Pump.

First row of roof panels on the north side

Installing the first row of roof panels on the north side

All the panels are numbered

All the panels are numbered

End-of-day status

End-of-day status

Week 18, Day 3

Week 18, Day 3:

  • The rain arrived exactly as forecast
  • More good progress with the Structural Insulated Panel installation, despite the weather
  • The two roof windows were delivered
Week 18, Day 3

Week 18, Day 3

Unloading the second panel delivery of the day

Unloading the second panel delivery of the day

Positioning the first panel of the south roof

Positioning the first panel of the south roof

End-of-day view from the main camera location

End-of-day view from the main camera location

The crane, with boom retracted

The crane, with boom retracted

The crane is a Liebherr LTM 1040-2.1.