Week 68, Day 2

Week 68, Day 2:

  • More work on the door canopies, preparing to install the permanent waterproof membranes in place of the temporary polythene sheeting
  • Further progress on the preparations for the 14 low-level outside lights, which will be mounted on top of the stone cladding with their cables hidden within the cladding
Week 68, Day 2

Week 68, Day 2

Wiring for 1 of 14 outside wall lights (Nordlux Canto)

Week 65, Day 5

Week 65, Day 5:

  • More work on the door canopies, mostly the side door since the front door is nearing completion
  • Installation of the flat panel lights in the ceilings of the door canopies, to illuminate the area outside the doors
Week 65, Day 5

Week 65, Day 5

Side door canopy with some of the cedar cladding installed

Front door canopy with light installed

15W LED flat panel over front door