Week 33, Day 4

Week 33, Day 4:

  • More plasterboarding on the second floor, completing the bathroom
  • More electrical first-fix, bringing some of the wiring through into the Plant Room
Week 33, Day 4

Week 33, Day 4

Plasterboard over the bath pipework on the second floor

Plasterboard over the bath pipework on the second floor

Wires brought through into Plant Room after plastering

Wires brought through into Plant Room after plastering