Week 2, Day 2

Week 2, Day 2:

  • Installation of the shuttering (wooden formwork) within the old cellar, ready to hold the foundation concrete while it sets – see second photo below
  • Completing the rest of the digging for the foundations, including adding the extra-wide areas for where the steel posts will connect to the concrete foundations and need extra support
Week 2, Day 2

Week 2, Day 2

Shuttering in old cellar

Shuttering in old cellar, at south-east corner of the new house