Week 11, Day 3:
- Lots more progress on the external walls, now approaching the top of the first floor level and soon ready for another lift of scaffolding
- Good progress laying the flooring boards over the first floor joists, glued to each other and also to the joists and then screwed down
- The site survey for the windows and external doors, confirming the dimensions, finishes etc. so that the order can be formally placed with the Internorm factory in Austria
- This actually provided more questions than answers – see later updates