Week 11, Day 1

Week 11, Day 1:

  • Yet another delivery of a full lorry load of concrete blocks first thing in the morning (before 08:00); probably just one more required now
  • Lots more progress fitting the first floor joists, including the short fiddly ones between the two steel beams over the Living Room
  • A bit more progress with the blockwork and a lot of preparation for installing the outer walling blocks in the coming days
  • Feedback to the manufacturers of the SIPS roofing units on their drawings for the roof structure, following the site meeting with the architects last week
Week 11, Day 1

Week 11, Day 1

Concrete Block Delivery

Concrete Block Delivery