Week 78, Day 5

Week 78, Day 5:

  • More snagging and general tidying up
  • The final inspection visit from the Building Control Officer who will now proceed to issue the Completion Certificate
  • Installation of the Orifice Plate to restrict the flow out of the Swale that takes the rainwater from the roof, in the unlikely event of the swale ever filling to the level of the outlet
Week 78, Day 5

Week 78, Day 5

60mm Orifice Plate at the outlet from the Swale

The north side of the house is now looking tidier

Week 78, Day 4

Week 78, Day 4:

  • Mostly a day of minor snagging on the inside, with little visual change but now the stairs don’t squeak and some floor tiles that had come loose have been re-fixed
Week 78, Day 4

Week 78, Day 4

The somewhat temperamental time-lapse camera on the pole at the south-east of the site has started working again so here’s a shot from that direction.

Camera 1 view from the south-east