Outbuildings: Week 38, Day 2

Outbuildings: Week 38, Day 2

The long-awaited concrete headwall was finally delivered and quickly installed and connected up to the flow-control chamber ‘downstream’.

Concrete headwall installed at the West end of the stormwater attenuation pond

With the outfall from the pond taken care of, work can proceed to level off the base of the pond before moving on to install the inlet – though there will need to be a bit of tidying-up of the pond walls around the headwall at some point.

The small load of ready-mixed concrete that had been ordered to reinforce the foul drainage pipe under the access road to the block-paved parking area arrived as scheduled. Once that has set the stone foundation for that access road can be installed, making the parking area and the garages accessible.

Foul drainage pipe between the House and the Biorock sewage treatment plant encased in concrete

I also completed a bit more preparation of the rainwater harvesting system by installing the submersible pump in the underground tank and routing its electrical cables and delivery hose to the pump controller in the adjacent building. A quick test of the pump, to flush through the delivery hose before connecting that to the inlet on the controller, showed it is working well. At their next visit, the plumbers should be able to get the rainwater supply working within the Outbuildings – since they’ve already fitted the meter, the expansion vessel and most of the other components required to enable that.

Outbuildings: Week 38, Day 1

Outbuildings: Week 38, Day 1

The main build team were on site all day sorting out a few of the smaller groundworks tasks:

  • Finishing the installation of the last of the Marshalls GrassGuard blocks around the perimeter of the block-paved parking area
    • There’s around 2/3 of a pack left over but those will be saved for future use
  • Filling in the holes excavated to access the water mains and electrical ducts
  • Clearing a trench around the foul drainage pipe that runs under what-will-be the vehicle access to the parking area, so that can be encased in concrete to maintain its level even with traffic passing relatively closely over the top of it
Completed block-paved parking area with its GrassGuard block perimeter / buffer area which then transitions to topsoil that will grow grass

The right-sized replacement concrete headwall was allegedly due for delivery today but is now said to be coming tomorrow.