Outbuildings: Week 30, Day 5

Outbuildings: Week 30, Day 5

With wet and windy weather forecast all day, the main build team had planned to work indoors: adding the second layer of loft insulation where the MVHR ductwork has been completed and finishing off the airtight taping around the edge of the plasterboard ceiling over the Workshop and Utility Room.

Outside, the rainwater tank was installed – with about a 400mm adjustment to the excavated hole when it became clear the tank’s access cover would not line up with the paved path it needs to be contained within. (That alignment was always planned but for some reason the hole was dug slightly out of position.) The adjustment meant removing the tank, making the hole wider, re-levelling the 100mm pea gravel base layer then installing the tank again. With the tank confirmed as being in the correct location it needed to be 1/3 filled (so 1,666 litres of water) to settle it into its base before commencing the back-fill of 300mm-deep layers of manually-compacted pea gravel. It took just over 2 hours to run in that much water through a hose – by which the time the heavy rain had arrived, so outside work was halted for the day.

It proved useful to have a water meter on the (to-be) ‘rainwater’ feed into the House, so that the volume of water being run into the tank from an outside tap could be measured more accurately than trying to judge 1/3-full by eye.

5,000 litre rainwater tank in-situ, photographed from the first floor of the House – looking somewhat dwarfed by the rest of the Courtyard (the tank is 2.3m wide, 2.89m long and 1.3m tall)

Despite the weather, there was further outdoor work – moving a few more lorry-loads of spoil off-site and taking delivery of more stone for the parking area.

The parking area to the North of the Garages being built up further with MOT3 stone, to allow drainage through the permeable block paving. The Aco threshold drain channels are also visible in the doorways.

Outbuildings: Week 30, Day 4

Outbuildings: Week 30, Day 4

Installation of the shower drain which will be integrated into the wet-room floor covering.

Wet-room shower drain installed into the space left within the original concrete floor slab

Also good progress with the airtight tape around the perimeter of the plasterboard ceiling in the Workshop, helping to provide a long-lasting airtight seal preventing air leakage into the roof space. (The idea is to restrict the air movement to happen via the MVHR unit’s heat exchanger, avoiding uncontrolled leakage elsewhere within the building fabric.)

The rainwater harvesting tank was delivered mid-morning, enabling its dimensions to be checked and the hole for it (that had been started yesterday) to be completed. The hole is roughly 2.5m wide, 3m long and 1.75m deep.

Hole dug into hard clay in the Courtyard for the rainwater harvesting tank

The threshold drain channels for the Garage doors were also delivered, and some more of the spoil from the landscaping in the Courtyard was removed off-site.

The electrical team were also back on site for the first time in about 10 days, continuing their first-fix in the two-storey section at the West of the building.