Outbuildings: Week 23, Day 4

Outbuildings: Week 23, Day 4

A little more progress on the roof tiling, but mostly some more fiddly (and much less obvious) work on the mortar fill on the gable verges and on the lead flashing where the roof butts up against the Garage wall. Work did start on the ridge tile installation but that highlighted the ventilated dry ridge kits that had been ordered were not the ones listed in the specification, so the correct ones now need to be sourced before the ridge tiles can be installed.

Also the completion of the in-roof solar PV panel installation, which started yesterday – a total of 24 460 Wp panels in a 12 x 2 configuration, for a maximum of 11 kWp of generation capacity. The panels needed to be installed now, before the roof tiling could be completed, and before the scaffolding gets taken down. The inverter and batteries will be installed much later, once there’s power and network connectivity available for their commissioning.

Completed in-roof solar PV installation, now ready for tiling around the array

The solar panel array is intentionally positioned off-centre on the roof to reduce the tendency for it to be shaded by the house in late afternoon. There will still be some shading, so the 24 panels have been wired as 3 groups of 8 (left, middle, right) feeding 3 separate MPPT inputs on the inverter.

Outbuildings: Week 23, Day 3

Outbuildings: Week 23, Day 3

Another day over 30C, making for difficult working conditions on site. More roof tiling – the start of work on the North-facing section of the Garage roof.

First (Eastern) set of roof tiles on the North section of the Garage roof

Also the start of the installation of the GSE in-roof tray system for the solar panels, on the South-facing section of the Garage roof.

First row of GSE in-roof trays for the solar panels, with lead flashing below