The main member of the on-site build team is away on holiday for a few days but the groundworks team were on-site to make progress with the complicated maze of pipes and ducts at the Western end of the Courtyard. There’s a Blue duct ready for the two 32mm MDPE water pipes (which were found next to the foundation for the retaining wall) and – not in the photo below – another duct for the communications cables.
More progress with the groundworks at the Western end of the Courtyard
There’s a bit of re-work required for the rainwater drain pipe running diagonally across by the doorway – that’s ended up too high to have any sensible ‘cover’ below paving, so it’s going to be moved slightly to the right and swapped with the vent pipe for the sewage plant (which is what is forcing it ‘high’).
Filling the gap between the Garage floor slab and the four threshold drains with concrete (which should dry to better-match the colour of the floor slab). As previously noted, the Garage Doors (roller shutters) will sit behind the brickwork openings.
Fresh concrete fill between the garage floor slab and the Aco threshold drain
In the Courtyard, more progress with making all the connections required around and to the West of the rainwater tank:
The blue ‘pipe’ in the photo below is a duct that will hold pipes and cables for the rainwater tank, bringing those to the control unit inside the ‘stable’
One flexible ‘pressure’ pipe for rainwater under pressure from the submersible in-tank pump
One mains supply cable for the pump
One flexible pipe to carry mains top-water into the tank in the event of the level falling below a threshold
One mains cable for the water level switch, mounted on the pump, to control the solenoid valve for the mains top-up – switching it on when the water level in the tank is too low then off again when it has risen (slightly)
The short pale grey ‘pipe’ is a duct which will be replaced with a much longer one and will contain data cables connecting the House to the Outbuildings
There need to be so many brown drain pipes – at different levels – to separate:
The fresh rainwater from the downpipe at the far left, heading for the inlet to the rainwater tank
The ground-level and land-drain drainage which needs to ‘bypass’ the rainwater tank (connected at the ‘covered’ inspection chamber nearest the camera)
The overflow from the rainwater tank, which needs a dedicated connection to a non-return valve (accessible via the ‘open’ inspection chamber)
The 32mm incoming mains and harvested-rainwater pipes still need to be installed, between the two ducts.
Fortunately, downstream of the non-return valve, all the drainage pipework can be brought together in a single 160mm pipe to exit the Courtyard, so from there on things get much simpler.
Maze of pipes and ducts to the West of the rainwater tank
Also, completion of the loft insulation over the Workshop and Utility Room, in readiness for the ceiling being skimmed with plaster in the coming days.