Week 62, Day 3

Week 62, Day 3:

  • The builder are back on site so I’m picking up with the daily updates from today
  • I’m still calling this “Week 62” since it’s the 62nd week of the build, allowing for the Christmas holidays in 2015 and 2016
  • Most of the activity was clearing out and cleaning up the site cabins since they’re being collected tomorrow, so no actual build progress today
  • The steel columns for the over-door canopies were delivered though

Week 62, Day 3

Galvanized steel columns for over-door canopies delivered ready for installation

 

 

Week 55, Day 5

Week 55, Day 5:

  • More tidying up of the site, most notably stacking the waste wood to make a bonfire for Bonfire Night
  • Some minor re-grinding of the polished concrete floor to remove a few scratches and even things up around one of the recessed floor boxes, followed by an overall re-sealing and re-buffing of all the polished concrete areas
  • A delivery of concrete blocks for the retaining wall
Week 55, Day 5

Week 55, Day 5

Bonfire from waste wood, old pallets etc.

Bonfire from waste wood, old pallets etc.