Week 35, Day 5

Week 35, Day 5:

  • The “south” camera has been going offline occasionally (maybe it’s all the rain?) and as a result there are no time-lapse photos from that camera today, so here’s one from the “north” camera instead
  • More plastering on the Second Floor, including skimming the ceiling in the Office
  • More progress with the pipework for the Ground Source Heat Pump in the Plant Room
Week 35, Day 5

Week 35, Day 5

Plaster skim coat complete on the Office ceiling

Plaster skim coat complete on the Office ceiling

Pipework progressing in the Plant Room

Pipework progressing in the Plant Room

Week 34, Day 5

Week 34, Day 5:

  • Some very heavy rain showers, hence the generally-damp look and the muddy puddles
  • The Ground Source Heat Pump and its accompanying tanks were delivered ready for installation next week
  • Some more electrical first-fix, mostly low-voltage cabling to the LED down-lighters from their (remote) drivers
  • Battening out the Master Bedroom walls and (sloping) ceiling ready for plasterboard – see photos below
Week 34, Day 5

Week 34, Day 5

"3x2" battens on the sloping ceiling of the master bedroom

“3×2” battens on the sloping ceiling of the Master Bedroom

The battens on the ceiling need to provide clearance for some low-profile downlighters.

Slim battens on the north wall of the Master Bedroom

Slimmer battens on the north wall of the Master Bedroom