Outbuildings: Week 12, Day 4

Outbuildings: Week 12, Day 4

Still more progress on the scaffolding (though it’s not quite complete yet) and all the brickwork is being built up around the inside of the courtyard,

There are a couple of steel beams required – one to support the roof over the bumped-out section of the Garages and another above the bi-fold doors at the end of the Workshop. Those are being designed by a structural engineer.

Week 41, Day 3

Week 41, Day 3:

  • I’ve probably not done the continued good progress on the plastering justice in recent posts so there’s a photo of the Living Room nearing completion
  • The ceiling of the balcony has been insulated, including the steel beams
  • The kitchen is progressing, with all the drawers now installed
  • More second-fix electrical and plumbing

Week 41, Day 3

Week 41, Day 3

Plastering in the Living Room

Plastering in the Living Room

Insulation over balcony

Insulation over balcony

Kitchen units almost ready for appliances

Kitchen units almost ready for appliances