Week 65, Day 5

Week 65, Day 5:

  • More work on the door canopies, mostly the side door since the front door is nearing completion
  • Installation of the flat panel lights in the ceilings of the door canopies, to illuminate the area outside the doors
Week 65, Day 5

Week 65, Day 5

Side door canopy with some of the cedar cladding installed

Front door canopy with light installed

15W LED flat panel over front door

Week 65, Day 3

Week 65, Day 3:

  • More work on the front door canopy
  • Tidying up some loose ends on the electrics:
    • Routing the supplies to the mirror heaters through KNX relays so they can be controlled automatically
    • Installing the wiring for the M-Bus meters which can be read automatically – these consist of:
      • Heat meters on the central heating and hot water circuits
      • Electricity meter on the supply to the heat pump – this meter actually has a pulse output but it’s connected to M-Bus via an adaptor
      • Water meters (x3)
  • As can be seen from the van in the photo below, the team from Alvaston Glass were back on site measuring up for the first batch of shower enclosures
Week 65, Day 3

Week 65, Day 3

Progress with the “hit and miss” cedar cladding on the front door canopy