Week 58, Day 5

Week 58, Day 5:

  • More progress on the ground works, back-filling behind the retaining wall and in the planters and levelling out the area by the side entrance
    • The lower section of retaining wall will be planted with ground-cover plants, and so it needs filling with topsoil and not the MOT 1 stone which can be seen in the photo, which will have to be dug out and replaced
    • This wall also needs lowering by one course of blocks so it lines up correctly with the middle step
  • A little more work on the outdoor electrics, setting galvanized steel conduit boxes into the blockwork and wiring the SWA cable into those for the outside lights and sockets
    • Most of the cables will be covered by the stone cladding
Week 58, Day 5

Week 58, Day 5

Back-filled retaining wall

Back-filled retaining wall

Levelled area by side door

Levelled area by side door

Cable boxes for outdoor lights and power sockets

Cable boxes for outdoor lights and power sockets

Week 58, Day 1

Week 58, Day 1:

  • Very heavy rain all day, hence the rain spots on the camera lens and the lights on inside at 3pm – and a mini lake on the driveway
  • Good progress with various of the internal snagging items and the installation of the remaining stair end-caps and the last of the oak for the glass balustrades
Week 58, Day 1

Week 58, Day 1

Last section of oak covering the fixings on the glass balustrades

Last section of oak covering the fixings on the glass balustrades

Completed end caps on the ground-to-first floor staircase

Completed end caps on the ground-to-first floor staircase