Week 49, Day 5

Week 49, Day 5:

  • At the moment a lot of the progress doesn’t show up in the pictures – there’s quite a lot of “soft” configuration of the lighting, security and heating systems where it doesn’t look like anything has changed
  • Since there’s a duct heater on the MVHR Supply to the house, the ducts down-stream of this need to be insulated to keep the heat inside the ducts so the air is still warm when it gets to the far end
    • The “hot” water supply to the duct heater is coming from the Ground Source Heat Pump and is therefore going to be warm rather than hot with most likely a relatively small effect on the air temperature
    • The small-bore plastic heating ducts are naturally better insulated than steel ducting and these were intentionally enclosed in the inter-floor insulation (more intended for acoustic rather than thermal purposes) so it’s really just the steel ducts and plenums in the Plant Room that need insulating
  • More work commissioning the lighting systems
    • Now all of the internal downlights and wall lights are installed and working, with just the LED strip lights and most of the outside lights to go
    • In the evening I completed the basic KNX programming so that the ceiling-mounted PIR switches in the bathrooms and hallways / landings control the relevant lights and the relatively small number of wall switches control the main lights in each room
    • The Up/Down light on the Balcony (a Nordlux Canto Maxi) has a pair of (allegedly) dimmable 5W GU10 LED bulbs controlled by an Aurora AU-DATR400 mains-voltage DALI dimmer. Compared to the excellent dimming behaviour of the internal lights with their separate DALI dimmers this combination isn’t anything like as good. More investigation required.
Week 49, Day 5

Week 49, Day 5

Partially-completed lagging on the ventilation ducts downstream of the duct heater

Partially-completed lagging on the ventilation ducts downstream of the duct heater

Balcony Up/Down Wall Light

Balcony Up/Down Wall Light

Week 49, Day 4

Week 49, Day 4:

  • Mostly completing the commissioning of the intruder- and fire-alarm systems
    • Some issues getting the CSL DualCom GradeShift unit to connect to the monitoring centre (EMCS) using an analogue telephone line in parallel with the mobile phone network in order to ensure a reliable connection
    • The unit is connected to a Cisco/LinkSys Analogue Telephone Adapter (ATA) which in turn connects to a Voice-Over-IP (VOIP) service which was expected to present a good-enough analogue telephone interface but something isn’t working right
    • It’s not currently clear whether it’s a simple configuration issue or whether it really does need a “proper” analogue telephone line (in which case it might be best to swap over to an IP network connection for the alternative communication path)
  • More work on the lighting drivers, connecting up most of the remaining circuits
  • More work on the finishing touches on the inside – e.g. skirting boards in the Open Plan area
Week 49, Day 4

Week 49, Day 4

BPM TUBE ceiling lights on the Second Floor Landing

BPM TUBE ceiling lights on the Second Floor Landing

Skirting Boards in the Open Plan area

Skirting Boards in the Open Plan area