Week 43, Day 5

Week 43, Day 5:

  • Lots of clearing up ready for the remainder of the scaffolding to be removed over the weekend
  • Good progress on the architraves and skirting boards on the second floor and starting to install the door furniture
Week 43, Day 5

Week 43, Day 5

Door furniture on Second Floor Bathroom

Door furniture, Second Floor Bathroom

Architraves and skirting boards, Second Floor

Architraves and skirting boards, Second Floor

Week 43, Day 4

Week 43, Day 4:

  • More oak flooring, this time on the first floor landing
  • Installing the furniture for the WC and the washbasin in the Family Bathroom
  • More external window reveals and sills
  • More second-fix electrical
  • More filling, sanding and painting around the recessed down-lights in the Open Plan area
Week 43, Day 4

Week 43, Day 4

Engineered oak flooring on the first floor landing

Engineered oak flooring on the first floor landing

Furniture in Family Bathroom

Furniture in Family Bathroom

Painting around the plaster down-light surrounds in the Open Plan area

Painting around the plaster down-light surrounds in the Open Plan area