Week 41, Day 2

Week 41, Day 2:

  • Quite a busy day – the 16:00 time-lapse snapshot caught one of the solar panels being installed
    • The 18 panels and the inverter are now Installed but not Commissioned
  • Installation of the first batch of oak flooring, in the Home Office on the Second Floor
  • More work on the kitchen installation
  • More plastering and second-fix electrical
  • Slightly re-working the membrane roof covering for the balcony floor to make sure any water drains properly
Week 41, Day 2

Week 41, Day 2

Support frames for Solar PV panels installed, clamped to standing seams on zinc roofing

Support frames for Solar PV panels installed, clamped to standing seams on zinc roofing

View from main camera location with Solar PV panels installed

View from main camera location with Solar PV panels installed

SolarEdge inverter installed in Plant Room

SolarEdge inverter installed in Plant Room

Oak flooring installed in Office on Second Floor

Oak flooring installed in Office on Second Floor

Second day of kitchen installation

Second day of kitchen installation

Week 41, Day 1

Week 41, Day 1:

  • The last section of zinc roofing on the south roof got completed, ready for the Solar PV installation (tomorrow)
  • The kitchen units were delivered, unpacked and roughly positioned
  • More second-fix plumbing, taking delivery of the remaining basins and toilets and installing some more of the basins
  • More second-fix electrical, mainly in the Plant Room
Week 41, Day 1

Week 41, Day 1

Kitchen unit delivery

Kitchen unit delivery

Kitchen island units and sink units beyond

Kitchen island units and sink units beyond

Basin in En-Suite for Bedroom 3

Basin in En-Suite for Bedroom 3