Week 39, Day 2:
- More plastering
- More second-fix plumbing and electrical, cutting out holes for the down-lights and PIR sensors (used in bathrooms and on landings)
- Completing the external insulation of the SIPS panels around the clerestory windows
Week 39, Day 1:

First few sections of zinc on the vertical face of the north roof installed by 10am, zinc panel forming machine in the foreground
The zinc panels don’t stay that shiny for long – the panels on the south roof have already gone a duller colour after the first rain shower.

No further zinc installed on the south roof but preparation for the cedar cladding around the clerestory windows
The hot water runs through a temperature regulator valve upstream of the wall-mounted mixer valve (out of shot), and the outlet from the mixer enters the bath via the “overflow”.