Week 38, Day 5

Week 38, Day 5:

  • More progress with the zinc roofing, nearly completing the south roof and starting to install the underlay on the north (curved) roof
  • More electrical second-fix – computer network outlets and light switches on the second floor
  • More plastering, getting the bathrooms ready for tiling (and better visibility of the plaster in the stairwell now the internal scaffolding has been removed)
Week 38, Day 5

Week 38, Day 5

Wider view from main camera location

Wider view from main camera location

Closer view of zinc on south roof

Closer view of zinc on south roof

Structured roofing underlay on vertical section of north roof

Structured roofing underlay on vertical section of north roof

Computer network sockets adjacent to power sockets in home office

Computer network sockets adjacent to power sockets in home office

Momentary-action ("Press") light switch in home office

Momentary-action (“Press”) light switch in home office

Completed plastering in En-Suite to Bedroom 3

Completed plastering in En-Suite to Bedroom 3

More-than-double-height space over stairwell

More-than-double-height space over stairwell

 

Week 38, Day 4

Week 38, Day 4:

  • Another day with a significant change visible from the time-lapse camera – the standing-seam zinc roof covering has started going on the south roof
  • Second-fix has started for the electrical installation, with mains sockets now installed on the second floor and the 9u, 19″ communications equipment rack mounted on the wall in the Comms Room on the second floor
  • More wet plastering, aiming to get the bathrooms ready for sanitaryware and tiling next week
Week 38, Day 4

Week 38, Day 4

Zinc roof installation underway

Zinc roof installation underway

Closer view of the zinc roofing status at the end of the day

Closer view of the zinc roofing status at the end of the day

Mains sockets in the home office on the second floor

Mains sockets in the home office on the second floor

Network communications cabinet mounted on the wall of the Comms Room

Network communications cabinet mounted on the wall of the Comms Room