Week 5, Day 3:
- More work to complete the concrete block cavity walls up to ground floor level, ready for the installation of the beam-and-block floor.
- Two steel wind-posts added to the west wall, adding structural support around a tall, narrow window.
The main camera still isn’t working so here’s another photo from Steve taken on Thursday morning, showing the steelwork.