Week 7, Day 1

Week 7, Day 1:

  • Completion of the last bit of below-ground blockwork walling
  • Laying of the oversite concrete in all but the two smallest rooms
Week 7, Day 1

Week 7, Day 1

Oversite concrete being poured

Oversite concrete being poured

Mostly-completed oversite concrete at the end of Week 7, Day 1 - just the Shower Room and Utility Room left to complete

Mostly-completed oversite concrete at the end of Week 7, Day 1 – just the Shower Room and Utility Room left to complete