Outbuildings: Week 37, Day 5

Outbuildings: Week 37, Day 5

A sub-zero night – and it didn’t make it far above freezing all day. The noon snapshot pleasingly caught frost on the shaded north-facing roof – which also shows the loft insulation is working OK in the Utility Room. (I’m not sure why the south-facing wall of the Garage often looks green in these photos, when the sun is bright – perhaps something is upsetting the camera’s attempt at white balance.)

The floor covering team were back on-site, laying the vinyl flooring. That will need further work on Monday, to weld the joints together, fit the threshold strips etc.

The plumbers were back too, though not for a full day. They completed the removal of the last of the redundant sections of underground water main – the main complication for that being that it was upstream of the on-site stop tap which meant the water needed isolating at the meter, which is 600 metres away. They also started fitting the water meters and expansion vessel for the rainwater harvesting system.

The heat pump team made a bit more progress, connecting up the pipework for the second indoor unit.

Outside, the main build team re-installed some of the rainwater downpipes with longer brackets, to clear the ductwork for the heat pump system, then continued work on the GrassGuard blocks – including starting to fill the voids in those with topsoil.

One of the rainwater downpipes reinstated with longer brackets, to hold it further from the wall making space behind for the horizontal trunking enclosing the pipework for the air-to-air heat pump

The long-awaited delivery of the new concrete headwall (and the collection of the one sent incorrectly) did happen as scheduled – while I was off-site turning off the water at the meter. When I got back I realised it looked wrong and checking the drawing confirmed it was a ‘small’ model (815mm high) not the required ‘medium’ model (1150mm high). The story is that it was a mix-up at the dispatch yard, where the one destined for here got labelled for another customer – so we got theirs. The plan is to swap them on Monday.

Outbuildings: Week 37, Day 4

Outbuildings: Week 37, Day 4

The floor covering team were back on-site, since they’re happy the self-levelling screed they laid on Monday has dried out enough for further work to proceed. They spent the day tidying up a few areas that weren’t as smooth as they’d like and fitted the ‘coved’ skirting and the capping strip that will cover the top of the vinyl. The weather has turned cold so it’s needing some heating in the Utility Room to make the flooring sheet pliable enough to lay and form up at the edges – ideally it wants to be 18C.

The plumber was back on site too, with the priority for them being the underground mains connections into the new building and removing some redundant underground pipe loops dating back to the House build. While those had been isolated via underground stop taps, it seemed unwise to trust those long-term, so the tee fittings were replaced with straight couplers. There’s just one more loop to remove tomorrow, once the hole dries out a bit more. Then two deep holes that have been open for a few weeks can be filled in.

There was also more progress on the GrassGuard perimeter to the block-paved parking area, which is starting to look much closer to being finished.

Ongoing progress on the Marshalls GrassGuard perimeter around the block-paved area

A larger digger and a dumper truck were also delivered in preparation for the arrival of the replacement concrete headwall, which is due tomorrow.