Week 48, Day 5

Week 48, Day 5:

  • More templating of the glass for the staircase – photo below
  • More second-fix electrical, installing and commissioning some more of the LED drivers
  • More work to complete the installation of the Ground Source Heat Pump, including installing the various temperature sensors (internal, external and on the hot water and heating buffer tanks)
Week 48, Day 5

Week 48, Day 5

Templates for the glass balustrade on the staircase

Templates for the glass balustrade on the staircase

Week 48, Day 3

Week 48, Day 3:

  • Good progress on the balustrade for the balcony, installing the brackets for the handrail and the clamps for the glass panel
  • Some initial preparations for finishing off the staircase
  • Nearing completion with the plumbing for the Ground Source Heat Pump
  • More second-fix electrical, mainly working on the 230V DALI dimmers for the mains-voltage lighting circuits
Week 48, Day 3

Week 48, Day 3

Support posts and clips for the glass balustrade on the balcony

Support posts and clips for the glass balustrade on the balcony

230V DALI dimmers for the First Floor

230V DALI dimmers for the First Floor