View of the Site from Chellaston Lane

The leaves suddenly seem to have dropped from the trees and now the site is more obvious from the lane. The hedge alongside Chellaston Lane was trimmed recently and looking over the hedge (which is still around 2m high) it’s possible to get an impression of how the house will look from the lane. Despite my best efforts the camera auto-focussed on the hedge so the background isn’t as clear as it might have been. (In my defence I’d like to point out that I was holding the camera at arm’s length over my head since otherwise it would have just been a photo of the hedge with nothing in the background.)

View of the site over the hedge on Chellaston Lane

View of the site over the hedge on Chellaston Lane, looking due north

While not all the features are particularly clear (better if you click the photo to zoom in) you should be able to make out, from left to right:

  • The grey steel frame of the house
  • The thin white pole which supports the time-lapse camera (between the wind turbines)
  • The splash of yellow which is the dumper truck parked on the floor of the old barn
  • The blue tarpaulin which is covering the stacked floor boards and joists on the floor of the old cow shed
  • The wooden pole which carries the electricity supply in on overhead lines from the right
  • The old steel hay barn in the next door field

The lighting in this photo highlights the wind turbines in the background. Those are located at the Severn Trent Water site at Spondon, 3 miles away, and they’re big – 80m to the top of the tower with blades 52m in length (so 132m from the ground to the top of the blades). More details here.

Electricity Supply Cable Upgrade Agreed

When the site’s previous electricity supply was reconnected in December 2013 for a very reasonable fee (as covered in some detail in this post) the agreement with Western Power Distribution (WPD), the local DNO, was that I would contact them again when the power supply requirements for the new house were better understood. They are particularly concerned about loads which have the potential to “disturb” the supply to neighbouring properties – in particular loads which have significant inductive characteristics, like big motors or arc welders – and any on-site generation above the 16A-per-phase threshold specified by the G83/2 guidelines (PDF link).

Right now the supply terminates in a green GRP cabinet near the electricity pole. The original plan was for that to be temporary and for the electricity meter to move into the Outbuildings with an onward feed to the House, but since the construction of the Outbuildings is being deferred the GRP cabinet will need to stay for a while and most likely for the long term. The plan is now to:

  • Install a new underground cable feeding the House, connecting to the GRP cabinet via the duct used for the temporary cable to the socket by the hedge on the southern boundary.
  • In due course, install another new underground cable feeding the Outbuildings, connecting back to the GRP cabinet via the duct used for the temporary cable to the caravan and site huts.
  • Make provision for the connection of a standby generator at the GRP cabinet, to provide a temporary supply in the event of an extended outage (e.g. due to the 11kV overhead cables being damaged). This was originally planned to connect at the Outbuildings but actually the GRP cabinet makes more sense since it’s further out of the way.

Had I wanted to move the meter then WPD would have had to take care of that, most likely re-cabling from the top of the supply pole to the new meter location, but since the meter is staying where it is there’s no need for any re-cabling for that purpose. However, there is a need for some re-cabling to cater for my preferred model of Ground Source Heat Pump, as noted in the Week 4, Day 5 post. I’d also like the option to install more than the G83/2 allowance of Solar PV in order to meet the Passivhaus Plus certification criteria.

The conclusion reached by the Western Power Distribution Team, following their site visit and the analysis of the data logging results, was that the thinner / older section of overhead cables were due a refresh anyway because of their age and due to evidence of previous damage and multiple repairs. The replacement cables would be of a slightly better specification (the same as the thicker / newer section of existing overhead cables) and would cater for the 32A start-up current of the NIBE F1145 GSHP as well as 5.5kWp of Solar PV generation capacity – all at no cost to me. In order for the work to proceed I had to sign WPD’s acceptance form saying I was happy with the terms of their zero-cost proposal, which I did today.

Most, if not all, of the re-cabling work will affect the fields owned by Thulston Fields Farm rather than my own property, so their consent is also required before the work can go ahead (plus a decision on whether to replace the poles and the overhead cables or whether to bury everything underground). There’s no particular hurry from my standpoint, as long as the work is completed before the GSHP system is ready to be commissioned (expected to be something like May / June 2016).

A lot of self builders seem to be unhappy with the service provided by their DNO but I must say I’ve been very happy with everyone I’ve dealt with at Western Power Distribution and I’m going to end up with a perfectly serviceable 15kVA grid connection for a very reasonable fee.